Saturday, August 8, 2009

8-7-09

We still are very much on schedule for our December 1st grand opening date. Things are happening faster and faster and more and more workers are on the site everyday.

At Possum Holler Bed and Breakfast the electrical and plumbing is pretty much all done. The insulation is being put into the walls. The Sheetrock has been delivered and is getting installed. The outside rock is on and the siding will start on Monday.


At the Bingo pavilion I was amazed at the number of bodies that where all under the roof. Speaking of roofs, the pavilion is all covered. They are finishing the knee wall around the perimeter of the building and the exterior walls are being put in.



They are moving dirt everywhere. The amphitheater is really taking shape and water treatment facility has been started. They will be putting in roadways and even start getting the major landscaping in the next couple of weeks.