Monday, October 12, 2009

51 days to go!

The progress continues to roll forward. I only got a quick stop out at the site over the weekend so this is going to be just a quick overview of the latest happenings all across the Country Crossing site.

The Possum Holler Bed & Breakfast continues to get the finishing touches done. The final coat of paint is going on most of the downstairs. All of the iron railings have been installed. The tile work is almost complete. The shower door have been installed. I spoke briefly with Blair and Ms. Cher, who have been hired to run the bed and breakfast, and they said that their house is starting to fill up with curtains, bedding, etc... All the stuff that they hope to shortly be able to move into the Bed & Breakfast and give it the real feel of home.



Parking lots continued to get paved, curbing put in, and where they can the sod is going down. This was the first time that I was able to drive through the main entrance and not the construction entrance. Very shortly a good portion of the roads will be pave which will cut down on the headaches that happens when it rains and the ground turns into a mud pit.



The biggest surprise for me was the amount of drywall that has been hung in the bingo hall in the last few days. When I was in a couple of days ago the right hand side of the main room of the Bingo Pavilion was covered but the left hand side was still mostly exposed metal studs. When I stopped by over the weekend I was amazed to see that the entire left hand side was now covered. The other big new item was the decorative crown piece that was being installed on the front of the building. It is details like this that will make this a world class facility that will attract national attention.

No comments:

Post a Comment